Blackwater gold project, Canada – update

Image of gold bars

Photo by ©Bloomberg

3rd May 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Blackwater gold project.

Location
Central British Columbia, Canada.

Project Owner/s
Artemis Gold.

Project Description
A feasibility study has shown several positive changes in the approach to the planned development of the Blackwater project, compared with the prefeasibility study (PFS) completed in 2020. 

Phase 1 throughput has been increased by 9%, from 5.5-million tonnes a year in the PFS to six-million tonnes a year in the feasibility study, with a larger crushing circuit providing greater operational throughput upside potential in the early years.

The accelerated Phase 2 involves the expansion to nine-million tonnes a year in Year 5, ramping up to 12-million tonnes a year in Year 6.

The increased production in years 1 to 5 supports a 29 % increase in average gold production over the first five years of operation, to 321 000 oz/y.

The Phase 2 expansion has been simplified and is to be achieved with only minor modifications to the existing Phase 1 crushing, stockpile and ball mill feed system. The second ball mill will operate in series with the Phase 1 mill. The rest of the plant circuits will be duplicated (gravity concentration, leaching, adsorption, elution and cyanide destruction) or expanded. Minor upgrades will be undertaken on some infrastructure to accommodate the increased throughput.

Phase 3 will increase production to 15-million tonnes a year in Year 10, ramping up to 20-million tonnes a year in Year 11.

The increased production in years 1 to 10 results in a 5% increase in the average gold production, to 351 000 oz/y of gold.

The Phase 3 expansion will require a new process line, from primary crushing to cyanide destruction, although a carbon elution circuit will not be needed, as the Phase 1 and 2 units will have sufficient capacity, with the lower ore-grades in Phase 3.  
 
Mining operations are proposed to cease in Year 17, with stockpiled ore rehandled and processed through the process plant in years 18 to 22. The decrease in mine life, from 23 years in the 2020 PFS to 22 years in the feasibility study, is a direct result of the increased throughput rate and production during the first ten years of the mine life in the feasibility study.  

Potential Job Creation
The total workforce at the Blackwater mine, including staff and contractors, surpassed 550 towards the end of December 2023.

Net Present Value/Internal Rate of Return
In the base case, the project has an after-tax net present value, at a 5% discount rate, of C$2.15-billion and an internal rate of return of 32.1%, with a payback of 2.3 years. This compares with an after-tax net present value, at a 5% discount rate, of C$2.25-billion and an internal rate of return of 35%, with a payback of 2.2 years in the PFS.

Capital Expenditure
Between C$730-million and C$750-million.

Planned Start/End Date
Construction is expected to start in the second quarter of 2022, putting the project on track to develop into a new tier-one gold operation in the first quarter of 2024.

Latest Developments
Construction of the Blackwater mine is continuing to progress on schedule, keeping it on track for first gold pour in the second half of the year.

At March 31, overall construction was about 73% complete, and about C$523-million of the guided capital budget of C$730-million to C$750-million had been spent, Artemis Gold reported on April 25.

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada, with the support of Knight Piésold; Moose Mountain Technical; Allnorth Consultants; Lorax Environmental Services; ERM Consultants; and JAT MetConsult (feasibility study).

Contact Details for Project Information
Artemis Gold, tel +1 604 558 1107 or email info@artemisgoldinc.com.

Edited by Creamer Media Reporter

Comments

Showroom

Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 
Hanna Instruments Image
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.155 0.21s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: